Daily Maintenance Tasks
1. Combustion System Inspection
- Verify proper flame pattern and color (blue with orange tips for gas)
- Check burner alignment and nozzle condition
- Monitor combustion air fan operation
- Record O₂ and CO levels (maintain 2-3% O₂, <100ppm CO)
2. Water Level & Feedwater Checks
- Test low-water cutoff controls
- Verify feedwater pump operation
- Check make-up water treatment system
- Monitor condensate return temperature (>180°F)
Weekly Maintenance Tasks
3. Safety System Verification
- Test safety relief valves (manual lift test)
- Verify flame safeguard system
- Check all pressure gauges for accuracy
- Inspect blowdown valves for leaks
4. Mechanical Components
- Lubricate all moving parts (bearings, linkages)
- Check belt tension on motor drives
- Inspect sootblower operation
- Verify damper operation
Monthly Maintenance Tasks
5. Internal Inspection
- Check for scale buildup (handhole inspection)
- Examine tubes for pitting or corrosion
- Inspect refractory lining for cracks/spalling
- Verify baffle condition and positioning
6. Water Chemistry Analysis
- Test boiler water alkalinity (maintain 700-1200 ppm)
- Check phosphate residuals (30-60 ppm)
- Monitor silica levels (<150 ppm)
- Verify oxygen scavenger residuals
Quarterly Maintenance Tasks
7. Comprehensive Cleaning
- Perform chemical cleaning if needed
- Clean heat exchanger surfaces
- Descale economizer tubes
- Clean burner diffuser plates
8. Efficiency Testing
- Conduct flue gas analysis
- Measure stack temperature
- Calculate combustion efficiency
- Verify heat transfer rates
Annual Maintenance Tasks
9. Complete System Shutdown Inspection
- Hydrostatic test pressure vessels
- Ultrasonic thickness testing of critical components
- Eddy current testing of tubes
- Calibrate all instrumentation
10. Documentation Review
- Update equipment logbooks
- Review maintenance history
- Verify compliance documentation
- Schedule next inspection interval
Special Condition Checks
- After Emergency Shutdowns
- Complete visual inspection
- Verify water chemistry balance
- Check all safety interlocks
- Test control system response
- Seasonal Preparations
- Winterize outdoor components
- Check freeze protection systems
- Verify summer ventilation requirements
- Inspect storm protection measures
Maintenance Record Keeping
- Log all completed maintenance tasks
- Record abnormal conditions
- Document parts replacements
- Track efficiency trends
Key Performance Indicators to Monitor
- Combustion Efficiency (Target: 85-95%)
- Steam/Water Loss Rate (<5% of total output)
- Fuel-to-Steam Ratio (Compare to design specs)
- Forced Outage Rate (Target: <1% of operating hours)
This comprehensive checklist helps maintain 98%+ boiler availability and can extend equipment life by 5-10 years when followed consistently. Always reference manufacturer specifications and adjust frequencies based on operational conditions.